Hanoi 2nd metro route elevated tracks to be tested
Trains will run 8.5 kilometers from Nhon in Bac Tu Liem District to the University of Transport and Communications in Dong Da District.
Operators and foreign experts will test the systems on six of the 10 trains that have arrived so far.
The elevated section is now 90 percent complete while the line, which will also run four kilometers underground, is 70 percent finished.
In all it will run 12.5 kilometers through the districts of Bac Tu Liem, Nam Tu Liem, Cau Giay, Ba Dinh, Dong Da, and Hoan Kiem.
Related News
Read More in This Category
HCMC considers new metro lines, more connectivity
Traffic news - 24/07/2023
The plan, announced by the HCMC Department of Transport, aims to synchronize the city’s urban railway network as part of the metropolis’ u...
NA members call for changing law to add birthplace to passports
Traffic news - 27/10/2022
The law does not require place of birth and this affects foreign relations and tourism, they said. Several countries like Germany, Spain, the Czech R...
Vietnam's biggest airport in the making still stuck at site clearance
Traffic news - 17/10/2022
Of the 2,532 ha of land earmarked for the first phase of the Long Thanh International Airport in Dong Nai Province that borders HCMC, the contractors...
Hanoi considers 6th metro line linking airport to new urban area
Traffic news - 14/10/2022
The Hanoi People’s Committee has requested relevant units to study the new line (Noi Bai-Ngoc Hoi) using non-refundable ODA from the Australian...